Pakse Urban Environmental Improvement Project

Project readiness filters and advanced actions are effective tools in mitigating the risk of startup and implementation delays. This project experienced a 2.5-year startup delay, which could have been minimized by implementing project readiness filters and advance actions, including procurement capacity building of the executing and implementing agencies during project preparation.