The implementation efficiency of the program was constrained by the late recruitment of the Technical Assistance Management Agency (TAMA), and the lack of recruitment of local support groups. The TAMA was meant to mobilize about 4,000 person-months of consulting services. The local support groups were expected to be mobilized in each district for 3 years to enhance capacity. For the majority of program implementation, these tasks became the responsibility of ADB and the program support unit (PSU), albeit with insufficient resources, which negatively affected implementation efficiency. A fully functional TAMA for the duration of the program would have allowed ADB to focus more on implementation of program reforms, rather than on technical assistance (TA) contract issues.
Punjab Devolved Social Services Program