The two-part approach of the TA project implementation was effective to flexibly accommodate changes in project environment and the government’s needs,and define the project scope for due diligence. Since CHP 5 construction was outside of direct control of the TA project, there were several occasions to change the technical specifications and subcomponent scope to accommodate the request from the CHP 5 concessionaire and the government.
Project Name
Preparing the Energy Efficiency and Urban Environment Improvement Project
Project Number
46343-002
Report Date
Report Source
Technical assistance completion reports