The key outputs in GMS TTF involve market liberalization and preferential treatment, e.g. exchange of traffic rights, resulting from negotiations between GMS Transport Ministers. As such, while engaging a lead expert to supervise various inputs to the implementation was effective at a technical level, intensive involvement of ADB staff is still required for policy dialogue at senior and ministerial levels in the GMS countries.
Project Name
Support for Implementing the Action Plan for Transport and Trade Facilitation in the Greater Mekong Subregion (Subprojects 1 and 2)
Project Number
44174-022
Report Date
Report Source
Technical assistance completion reports