Procurement is critical in infrastructure projects, requiring preparation by project/program design consultants and close supervision by consultants, the government and executing agencies, and ADB. Subprojects suffered major delays because of weak procurement, leading to substantive time and cost overruns. Program implementation team from ADB should have been more proactive in assisting in the implementation of startup activities such as consultant recruitment and preparation of engineering designs.