Improved Energy Access for Rural Communities

Drawing from similar past project experiences, as part of due diligence, will help minimize or avoid cost underestimations. The connection costs under this project were underestimated by 250%, resulting in the project installing only 43% of its planned 4,500 household connections. More thorough due diligence should have been carried out during project preparation, with cost estimates validated by experiences under similar past projects.

Project Name

Improved Energy Access for Rural Communities

Project Number
41504-024
Report Date
Report Source
Self-evaluation
Report Rating
Topics