Fifth Health Sector Development Project

High staff turnover worsens capacity constraints. In this project, it aggravated lack of capacity to undertake procurement using ADB's Procurement Guidelines and the increased risk of misconduct and delays during implementation. Additional procurement capacity building for executing agency staff during implementation is therefore necessary even if procurement capacity risk is considered minimal at project appraisal.