The participation of a financial management specialist in review missions and site visits will help improve capacity and ensure timely financial reporting. The project generally met ADB’s financial monitoring and reporting requirements. However, submission of the audited project financial statements was at times delayed. The delays could have been avoided by having a financial management specialist participate in project review missions and site visits. The measure could have also enhanced the capacity and awareness of ADB financial management procedures.
Project Name
Bihar Power System Improvement Project
Project Number
41626-013
Report Date
Report Source
Self-evaluation
Country
Themes
Applicability
Project Cycle Stage
Implementation