Changes in government may require a new or additional round of capacity- and awareness-building. The national election in 2012 resulted in a change in the government and subsequent appointment of new directors and staff in the Municipal Development Fund of Georgia (MDF), the project executing and implementing agency. Therefore, additional time had to be devoted to build capacity and awareness with respect to the project.