Sustainable Urban Transport Investment Program - Tranche 4

Timely reassessment can be instrumental to project success. After the project was approved, a series of devastating storms caused severe damage in the project area. The timely engagement of a consulting firm to revise the project design helped avoid project delays. Project interventions were revised based on the additional rehabilitation needs and the new evidence about potential impacts of storms on the coastline. The timely reassessment of the project’s detailed design after unforeseen external factors occurred was instrumental in maintaining the project’s relevance, strengthening the project results, and avoiding implementation delays.

Project Name

Sustainable Urban Transport Investment Program - Tranche 4

Project Number
42414-044
Report Date
Report Source
Self-evaluation
Country
Report Rating
Applicability
Project Cycle Stage
Implementation