East-West Corridor Project

The initial delay in project implementation was primarily caused by slow procurement, land acquisition, and resettlement activities. This is a common issue for all projects in India. Project implementation also experienced prolonged delays in clearance for cutting of trees. For ADB-funded projects, such constraints are now being addressed through a project readiness checklist and training and capacity building programs for the executing agencies. This will ensure that preconstruction activities are carried out in advance and only well-prepared projects are taken up for approval.

Project Name

East-West Corridor Project

Project Number
32253-013
Report Date
Report Source
Self-evaluation
Country
Report Rating