Late allocation of provincial counterpart funds is a persistent issue requiring attention from the central government of Viet Nam. Late allocation of counterpart funding slowed down implementation progress and exposed subprojects to additional cost increases through inflation. The central government should consider providing incentives for timely provincial allocations. It could also explore alternative funding arrangements to address the issue.