Late allocation of provincial counterpart funds is a persistent issue requiring attention from the central government of Viet Nam. Late allocation of counterpart funding slowed down implementation progress and exposed subprojects to additional cost increases through inflation. The central government should consider providing incentives for timely provincial allocations. It could also explore alternative funding arrangements to address the issue.
Project Name
Integrated Rural Development Sector Project in the Central Provinces
Project Number
37097-013
Report Date
Report Source
Self-evaluation
Country
Sector
Themes
Applicability
Project Cycle Stage
Implementation