Hairatan to Mazar-e-Sharif Railway Project

Implementing a project of this magnitude and in a strict timeframe was quite challenging. However, this can be achieved through exceptional involvement of donors. ADB provided enhanced supervision both from headquarters and the resident mission. Staffs were closely involved in identifying and promptly resolving issues. Any matter requiring ADB's internal approval was expedited and funds were released with fast-track processing. Furthermore, a fulltime implementation consultant was mobilized by ADB on site to provide coordination, implementation assistance, and independent reporting. All these factors contributed to timely resolution of implementation issues and completion of the project.

Project Name

Hairatan to Mazar-e-Sharif Railway Project

Project Number
42533-022
Report Date
Report Source
Self-evaluation
Country
Report Rating