The consulting services for project implementation designed during project preparation did not meet the needs during implementation. This usually happens because needs change over time. To avoid having to undertake contract variations to correct this balance, an approach used in European Union contracts would have allowed greater flexibility; bidders for consulting services are typically evaluated on a small number of long-term key experts; while short-term expertise is not defined in the bidding but decided upon during implementation based on agreed work plans and government demands.