It was noted at appraisal: �preparation of documentation and commencement of civil works for phases 2 and 3 will follow sequentially as individual tasks are completed under Phase 1.� This meant that delays and changes in some subprojects in phases 1 and 2, led to delays in subsequent Phase 3 subprojects. In future, this kind of conditionality should be avoided to prevent delays in implementation.
Project Name
Central Region Transport Networks Improvement Sector Project
Project Number
34356-013
Report Date
Report Source
Self-evaluation
Country