In ongoing and future projects, training and advice on ADB's safeguard policy and procedure need to be strengthened, and this should be extended to consultants and related personnel. Strong safeguards compliance monitoring by the executing agency, consultants, and ADB can help in timely resolution of any issues that emerge during project implementation. Furthermore, the survey of all the houses adjacent to the project road was good practice, and one which should be applied to all other ADB projects in the country.
Project Name
CAREC Transport Corridor 1 (Bishkek-Torugart Road) Project 1
Project Number
39674-022
Report Date
Report Source
Self-evaluation
Country