The costs of construction materials were underestimated. The price for some construction materials, such as cement, steel, stone, and sand increased substantially during project construction. Although there was a price escalation clause in the contracts, price negotiations and contract variations and approval of the variations took considerable time and caused delay in the financial closure of the project.
Project Name
Dali-Lijiang Railway Project
Project Number
36432-013
Report Date
Report Source
Self-evaluation