(Cambodia) Power Transmission Lines Co., Ltd., Power Transmission Project

The CPTL project itself offers a meaningful demonstration effect. It was well constructed and delivered electricity on time and to agreed specifications, in turn allowing EDC to deliver electricity to its customers. Under the PPA, EGAT delivers electricity to EDC via CPTL as agreed. EDC meets its contractual payment obligations to EGAT and CPTL. EAC monitors tariffs and licensees, allowing project benefits to be passed on to the end-users in the form of lower tariffs. For PPP investments to succeed, all the stakeholders that affect the perception of the investment environment must commit long-term support to PPPs, agreements must be documented, and all parties must fulfill documented contractual obligations. In the case of the CPTL project, these elements have all combined to allow CPTL to deliver impressive results, and this achievement is recognized.

Project Name

(Cambodia) Power Transmission Lines Co., Ltd., Power Transmission Project

Project Number
40914-015
Report Date
Report Source
Independent project evaluation
Country
Report Rating
Applicability
Keywords
NSO evaluation