Gansu Clean Energy Development Project

Strong project ownership is essential for successful implementation. In evaluating project ownership, attention must be given during appraisal not only to investment planning priorities but also to whether counterpart funding has been committed, key staff are in place, coordination mechanisms across and within different government levels are working effectively, and an institutional capacity exists to address social and environmental issues affecting the project’s long-term sustainability.

Report Date
Project Name

Gansu Clean Energy Development Project

Project Number
34476-013
Report Source
Independent project evaluation
Country
China, People's Republic of
Report Rating