Public Sector Program - Subprograms 1 and 2: Program Completion Report

The program's DMF was overambitious (para. 8) and, based on ADB guidelines for DMF preparation could have been correctly recast to make the outcome the intended impact and output 1 the intended outcome. The outcome and impact statements and indicators and targets in a DMF need to be realistic and take into account the country context. [Main text, para. 38]

Project Name

Public Sector Program - Subprograms 1 and 2: Program Completion Report

Project Number
43321-013
43321-023
Report Date
Report Source
Self-evaluation
Report Rating
Keywords
Design and monitoring framework (DMF).