Reform agendas chosen for program cluster support should be carefully selected during program design. Subprogram 1 had 25 policy conditions, while subprogram 2 had 38 policy conditions. The large number of implementing agencies and reform areas complicates program coordination. When reviewing the implementation of this cluster program, too often it seemed that quantity of policy actions was a substitute for the low number of consequent reforms that could be achieved within the indicative time-span.
Project Name
Sindh Growth and Rural Revitalization Program
Project Number
41545-013
41545-023
Report Date
Report Source
Self-evaluation
Country