Financial management assessments undertaken at appraisal need to fully assess the potential for executing agencies to provide the level of funding proposed in the project financing plan to avoid cancelation of project activities that may negatively affect project viability and sustainability.
Project Name
Regional Power Transmission Interconnection Project (Afghanistan and Tajikistan)
Project Number
40043-013
Report Date
Report Source
Self-evaluation