Structuring and implementing a PPP project is complex, time-consuming, and requires significant resources and commitment by all parties involved. Knowing that the PPP concept was at an early development stage in the Maldives at the time of project inception and that few ministries had the capacity or resources for PPP project development, ADB and the executing agency should have identified appropriate focal points and obtained stronger management commitment from relevant line ministries to ensure efficient implementation.
Project Name
Private Sector Development Project
Project Number
41149-013
Report Date
Report Source
Self-evaluation
Country