Lack of project readiness leads to project implementation delays. Completing requisite preparatory works prior to project approval maximizes the possibility of timely project implementation by giving adequate attention to construction quality and sustainability of facilities. Proper provisioning and implementation of advance procurement and retroactive financing can also minimize implementation delays.
Project Name
Rural Reconstruction and Rehabilitation Sector Development Program
Project Number
40554-022
40554-032
Report Date
Report Source
Self-evaluation
Country