Rural Reconstruction and Rehabilitation Sector Development Program

Lack of project readiness leads to project implementation delays. Completing requisite preparatory works prior to project approval maximizes the possibility of timely project implementation by giving adequate attention to construction quality and sustainability of facilities. Proper provisioning and implementation of advance procurement and retroactive financing can also minimize implementation delays.