Community Water Transport Project

While the issue of delays to project mobilization were recognized in the lessons learned at appraisal, the project failed to ensure such delays did not occur. Future projects need to plan for timely advance procurement of consultants and ensure advance commitment to institutional and financing arrangements prior to loan approval. Where trust funds are part of project design, institutional and operating rules need to be agreed and trust deeds formulated and agreed, if not formally signed prior to loan approval. Advance appointment of fund managers should be considered. In the Papua New Guinea context, arrangements to avoid or fast-track the Central Supply and Tenders Board/National Executive Council procurement process need to be considered for incorporation in project loan agreements.

Project Name

Community Water Transport Project

Project Number
34121-013
Report Date
Report Source
Self-evaluation
Report Rating