Affected households should be provided with full information regarding their entitlements, livelihood options, and access to other services; and to secure their agreement for proposed resettlement sites as early as possible. The project owner should proactively engage in the consultation process, without delegating the responsibility for managing the resettlement to local government agencies. Consultations with the affected people were not effectively conducted by the local government, which caused significant delays because of lack of consensus on the resettlement sites. This could have been avoided if ZPSC had played a more active role in managing the resettlement program.
Project Name
Hebei Zhanghewan Pumped Storage Project
Project Number
28212-013
Report Date
Report Source
Self-evaluation
Country