Skip to main content
Evaluation Lessons
  • Home
  • Countries
    • Afghanistan
    • Armenia
    • Azerbaijan
    • Bangladesh
    • Bhutan
    • Brunei Darussalam
    • Cambodia
    • China, People's Republic of
    • Cook Islands
    • Federated States of Micronesia
    • Fiji
    • Georgia
    • Hong Kong, China
    • India
    • Indonesia
    • Kazakhstan
    • Kiribati
    • Kyrgyz Republic
    • Lao People’s Democratic Republic
    • Malaysia
    • Maldives
    • Marshall Islands
    • Mongolia
    • Myanmar
    • Nauru
    • Nepal
    • Niue
    • Pakistan
    • Palau
    • Papua New Guinea
    • Philippines
    • Republic of Korea
    • Samoa
    • Singapore
    • Solomon Islands
    • Sri Lanka
    • Taipei,China
    • Tajikistan
    • Thailand
    • Timor-Leste
    • Tonga
    • Turkmenistan
    • Tuvalu
    • Uzbekistan
    • Vanuatu
    • Viet Nam
    • Australia
    • Japan
    • New Zealand
  • Sectors
    • Agriculture, natural resources, and rural development
    • Education
    • Energy
    • Finance
    • Health
    • Industry and trade
    • Information and communication technology
    • Multisector
    • Public sector management
    • Transport
    • Water and other urban infrastructure and services
  • Themes
    • Inclusive Economic Growth
    • Environmentally Sustainable Growth
    • Regional Integration
    • Private Sector Development
    • Governance and Capacity Development
    • Gender Equity and Mainstreaming
    • Knowledge Solutions
    • Partnerships
  • About
  • Home
  • Countries
  • Sectors
  • Themes
  • About

Tsunami-Affected Areas Rebuilding Project

In emergency situations, requiring design changes that are inconsistent with existing regulations should be avoided no matter how appropriate.

Project Name

Tsunami-Affected Areas Rebuilding Project

Project Number
39144-013
Report Date
29 Oct 2014
Report Source
Validation of self-evaluation
Country
Sri Lanka
Sector
Finance
Public sector management
Transport
Water and other urban infrastructure and services
Inclusive finance
Law and judiciary
Public administration
Road transport (non-urban)
Urban water supply
Themes
Environmentally Sustainable Growth
Inclusive Economic Growth
Gender Equity and Mainstreaming
Governance and Capacity Development
Report Rating
Successful

Related Lessons

More strategic and participatory planning is desirable. LGU chief executive officers (CEOs) often selected subprojects and made investment…


Adequate consultation and better communication with affected people for projects experiencing resettlement issues can reduce implementation delays…


There is a need for closer ADB involvement in critical early stages and greater rigor in government reporting.


The sustainability of rural infrastructure interventions, mainly rural roads and irrigation schemes relies heavily on securing funds for their…


Continued renewal of CTOs for WTPs and STPs by the PHED and project ULBs after handover of the assets by the IPMU is necessary for compliance with…


Subscribe to our mailing list

6 ADB Avenue,
Mandaluyong City
1550, Metro Manila,
Philippines

 

Phone: +632 632 4444
Fax: +632 636 2444

Other ADB Websites

ADB Compliance Review Panel
Asia Pathways (ADBI Blog)
Asia Regional Integration Center
Asian Bonds Online
Asian Development Blog
Open Access Repository
Statistical Database System

IED Social Media

LinkedIn

Twitter

YouTube

©2024 Independent Evaluation - Asian Development Bank

Footer

  • About