Ministry of Industries, Production, and Special Initiatives (MoIPSI) and the project management unit (PMU) had difficulty in understanding the requirements of the design and monitoring framework (DMF) because it lacked clarity regarding activities and output requirements. The PMU noted that, even though terms of reference had been prepared for individual consultants, the exact purpose of some of the positions and the outputs to be delivered were not clear. Review missions need to ensure that the project management fully understands the requirements of the DMF regarding achievement of activities and outputs.
Project Name
Rural Enterprise Modernization Project
Project Number
38447-013
Report Date
Report Source
Self-evaluation
Country