An effective project implementation entity is important when multiple financiers are involved, in order to ensure uniform standards in the construction of the project road. For the ADB-funded section of the road, the Lao PDR government could keep track of expenditures and verify if timelines and guidelines are followed. This was not the case with the PRC and Thailand financed sections. For example, the PRC used its own design standards for the road without conducting any dialogue with the Lao PDR government.
Project Name
Greater Mekong Subregion: Northern Economic Corridor Project in the Lao People’s Democratic Republic
Project Number
34231-013
Report Date
Report Source
Independent project evaluation
Country