Need to constantly follow-up with the executing agency on the implementation of the project performance and monitoring system. It is surprising to note that this loan condition was not readily achieved, although its compliance was considered as ongoing.
Project Name
Dali–Lijiang Railway Project
Project Number
36432-013
Report Date
Report Source
Validation of self-evaluation
Country