Punjab Millennium Development Goals Program - Subprograms 1 and 2

One of the PMDGP's (Punjab Millennium Development Goals Program) principal lessons is that interventions in countries with difficult socioeconomic conditions and generally weak implementation capacity require more comprehensive due diligence during design. When large complex programs are prepared in this context, ADB needs to carry out detailed, rigorous, and objective analysis of the potential implementation risks, especially those related to the executing agency. Once that is done, all necessary mitigation measures must be built into the design.

Project Name

Punjab Millennium Development Goals Program - Subprograms 1 and 2

Project Number
41641-013
Report Date
Report Source
Self-evaluation
Country
Report Rating