Second Rural Infrastructure Improvement Project

Need for a high-level coordinating body. For a complex, multicomponent project, regular monitoring of implementation progress by the government through a high-level and active plenary body or steering committee is indispensable. Regular interaction among the borrower, stakeholders, consultants, contractors and suppliers, and ADB through the executing agency's PMO (project management office) contributed greatly to the success of the project.