In any project implementation, it is much more efficient to identify and correct problems in the initial part of the project period. The frequency of ADB review missions in the initial phase of the project achieved this efficiency and did a great deal to prevent further delays. The lesson is to have a higher frequency of review missions in the early phase of project implementation.
Project Name
Kunming-Haiphong Transport Corridor-Noi Bai-Lao Cai Highway Technical Assistance Project
Project Number
33307-023
Report Date
Report Source
Self-evaluation
Country