Originally a total of $0.5 million was allocated to the capacity development component, but only $0.01 million was actually spent. Additional attention could have been given at appraisal to properly identify and cost each part of the capacity development component.
Report Date
Project Name
CAREC Transport Corridor I (Bishkek-Torugart Road) Project 2
Project Number
42399-013
Report Source
Self-evaluation
Country
Kyrgyz Republic
Themes
Keywords
Capacity development component.