CAREC Transport Corridor I (Bishkek-Torugart Road) Project 2

During construction of At-Bashy road, some disputes arose between the contractor and the local population, causing late completion of minor but essential works e.g. sidewalks and drainage. Information on these incidents was not promptly reported to all parties concerned. Not being fully aware of the situation, IPIG (Investment Projects Implementation Group) initially advised ADB that there was no need to extend the loan and grant closing period. However, when the extent of remaining works to be completed became apparent, an extension was provided. This issue was swiftly resolved. It is important to ensure proper communication between contractors, consultants project implementation unit and, ADB by fielding an ADB mission to help dispute resolution. It is also vital to field ADB missions to coincide with the completion of physical works, to enable the mission to verify completeness of such works and assist in determining whether loan and/or grant extensions are needed.

Project Name

CAREC Transport Corridor I (Bishkek-Torugart Road) Project 2

Project Number
42399-013
Report Date
Report Source
Self-evaluation
Country
Report Rating
Keywords
Communication