Skip to main content
Evaluation Lessons
  • Home
  • Countries
    • Afghanistan
    • Armenia
    • Azerbaijan
    • Bangladesh
    • Bhutan
    • Brunei Darussalam
    • Cambodia
    • China, People's Republic of
    • Cook Islands
    • Federated States of Micronesia
    • Fiji
    • Georgia
    • Hong Kong, China
    • India
    • Indonesia
    • Kazakhstan
    • Kiribati
    • Kyrgyz Republic
    • Lao People’s Democratic Republic
    • Malaysia
    • Maldives
    • Marshall Islands
    • Mongolia
    • Myanmar
    • Nauru
    • Nepal
    • Niue
    • Pakistan
    • Palau
    • Papua New Guinea
    • Philippines
    • Republic of Korea
    • Samoa
    • Singapore
    • Solomon Islands
    • Sri Lanka
    • Taipei,China
    • Tajikistan
    • Thailand
    • Timor-Leste
    • Tonga
    • Turkmenistan
    • Tuvalu
    • Uzbekistan
    • Vanuatu
    • Viet Nam
    • Australia
    • Japan
    • New Zealand
  • Sectors
    • Agriculture, natural resources, and rural development
    • Education
    • Energy
    • Finance
    • Health
    • Industry and trade
    • Information and communication technology
    • Multisector
    • Public sector management
    • Transport
    • Water and other urban infrastructure and services
  • Themes
    • Inclusive Economic Growth
    • Environmentally Sustainable Growth
    • Regional Integration
    • Private Sector Development
    • Governance and Capacity Development
    • Gender Equity and Mainstreaming
    • Knowledge Solutions
    • Partnerships
  • About
  • Home
  • Countries
  • Sectors
  • Themes
  • About

Kolkata Environmental Improvement Project

Project timelines need to take into account implementation complexity, the experience of the executing agency, consultants and contractors, and the available working seasons.

Project Name

Kolkata Environmental Improvement Project

Project Number
29466-023
Report Date
11 Sep 2015
Report Link
https://www.adb.org/projects/documents/kolkata-environmental-improvement-projec…
Report Source
Self-evaluation
Country
India
Sector
Water and other urban infrastructure and services
Urban policy, institutional and capacity development
Themes
Environmentally Sustainable Growth
Inclusive Economic Growth
Gender Equity and Mainstreaming
Governance and Capacity Development
Report Rating
Successful

Related Lessons

An effective project implementation entity is important when multiple financiers are involved, in order to ensure uniform standards in the…


Strong contractor qualification criteria and stringent contractual provisions on contractor performance are needed to ensure the timely completion…


The ability of all participating utilities to successfully adopt and implement organizational changes to meet the project requirements should be…


SAOD highlighted further the importance of developing strategic partnerships in advancing climate change solutions. Leveraging knowledge…


To confirm the economic viability of the regional plan and then identify which countries benefit or do not benefit, an economic internal rate of…


Subscribe to our mailing list

6 ADB Avenue,
Mandaluyong City
1550, Metro Manila,
Philippines

 

Phone: +632 632 4444
Fax: +632 636 2444

Other ADB Websites

ADB Compliance Review Panel
Asia Pathways (ADBI Blog)
Asia Regional Integration Center
Asian Bonds Online
Asian Development Blog
Open Access Repository
Statistical Database System

IED Social Media

LinkedIn

Twitter

YouTube

©2024 Independent Evaluation - Asian Development Bank

Footer

  • About