Where country systems are weak, program monitoring could benefit from TA (technical assistance), as in Tajikistan. The TA could focus on expenditure tracking mechanisms, internal controls, and external audits; and be conducted in two stages. In the first stage, when monitoring capacity is still weak, experts could be engaged to monitor program-supported expenditures rather than relying on the government to submit monitoring reports. The second stage would focus on improving country systems to help the transition of monitoring tasks from external experts to government staff.