Integrated Urban Development Sector Project

For projects where machinery and equipment are to be purchased from project funding, it should be ascertained during project design that the executing agency is making sufficient allocations to the operational budget in the year targeted for the procurement of the equipment, and the years to follow. Otherwise, the equipment is not used effectively for lack of operational budget in the first year.

Project Name

Integrated Urban Development Sector Project

Project Number
38160-032
Report Date
Report Source
Self-evaluation
Country
Report Rating