Need for timely taking over of completed project sections by the government. At completion, the taking over of section 1 by Uzavtoyul was delayed due to administrative problems within the government. This contributed to poor maintenance after the defects liability period. This issue was resolved in 2014. Future taking over of completed road sections needs to be conducted in a timely manner by the government.
Project Name
CAREC Regional Road Project
Project Number
39669-013
Report Date
Report Source
Self-evaluation
Country