The timely availability of counterpart funding prevented cash flow problems from arising, which could have delayed project completion. Because counterpart government funding was timely, there were no delays and the project was completed early.
Project Name
Gansu Heihe Rural Hydropower Development Investment Program— Erlongshan Hydropower Project
Project Number
39652-023
Report Date
Report Source
Independent project evaluation
Country