Enhancing Education Quality Project

The executing agency and the national project implementation team need to have adequate capacity to undertake the varied roles required in a broad project like this. Such roles as procurement, management of civil works contracts, record keeping, monitoring, and evaluation are just some of the necessary attributes required of a project management team. If the capacity is not present at inception, then part of the initial implementation process should include provision for on-the-job training and capacity building. In this project, the lack of capacity caused implementation delays but these were eventually overcome and the project was closed on time.