Extension of the defects liability period can enhance the sustainability of first-of-their-kind advanced technologies like the project’s newly built 500-kV GIS.
Project Name
Nurek 500 kV Switchyard Reconstruction Project
Project Number
42189-012
Report Date
Report Source
Self-evaluation
Country