Although the supporting TA addressed issues related to budget preparation and execution, continued support for the entire PFMR process is needed. The expectation that the TA could achieve its outcome within 24 months was too optimistic based on capacity constraints, which should have been identified at appraisal.
Report Date
Project Name
Public Finance Management Reform Project
Project Number
41041-013
Report Source
Validation of self-evaluation
Country
Uzbekistan
Applicability
