The number of projects and subprojects to be implemented under any assistance package must consider the absorptive capacity of local contractors, availability of construction materials, and local labor. Close attention must be given to the quality of the facilities and infrastructures built. Utilizing local contractors and labor have their trade-offs, such as implementation delays and deficiency in financial resources, but the quality of the completed facilities is nonnegotiable. This would require closer supervision, frequent monitoring, and faster processing of payments.
Project Name
Conflict-Affected Region Emergency Project
Project Number
44065-013
Report Date
Report Source
Validation of self-evaluation
Country
Sector
Themes
Applicability