MFF-Madhya Pradesh Power Sector Investment Program (Tranche 5)

Regarding results framework and methodology level lessons, this validation suggests that since one of the MFF outcomes was for better financial performance of the distribution companies, ADB should emphasize more on the monitoring of financial performance over the 5 or more years of project implementation. Improvement in the physical infrastructure of the power systems should go hand-in-hand with improvements in the financial soundness of these companies. Corrective measures to financial performance should be during implementation when ADB has the most leverage.

Project Name

MFF-Madhya Pradesh Power Sector Investment Program (Tranche 5)

Project Number
32298-063
Report Date
Report Source
Validation of self-evaluation
Country
Report Rating
Applicability