For greater effectiveness of the monitoring and evaluation framework of the project, the overall logic and results chains as well as indicators need to be firmly established and tested before project effectiveness. Three main aspects can be improved: (a) project attribution needs to be addressed in the methodologies used for collecting indicator data, (b) measuring the degree of infrastructure use by beneficiaries provides more accurate information of the project’s results than focusing on physical progress in construction, and (c) the development results of capacity building activities are better assessed through measurement of the degree of behavior change of beneficiaries.