Sector projects of a multisectoral nature face the risk of having implementation problems and achieving lower than expected development outcomes. Additional work at project design needs to identify and establish clear rules about the types of investments that are eligible for financing, ensuring that these contribute to the project’s stated outcomes. At implementation, a close communication of the rules for investment is critical to avoid delays stemming from extensive revisions to proposed investment plans.