Guangxi Wuzhou Urban Development Project

To avoid significant delays (4 years) in agreeing on compensation, careful consideration needs to be given to the following: (i) the location of the proposed house relocation site need to be close to the original houses; (ii) compensation rates offered should be higher due to cost inflation of construction materials; and (iii) the relocation sites need to be comparable.