Providing technical assistance to strengthen the institutional capacity of newly established states, executing agencies, and implementing agencies is essential. Capacity building activities should be included to enable smooth project execution according to ADB guidelines. The risk of natural disasters needs to be considered better during project design. More thorough due diligence into the frequency of these events needs to be employed, as for example the Sobla-1 hydropower plant was washed away twice, resulting in the abandonment of the project.