Strengthening Water Management and Irrigation Systems Rehabilitation Project

Project procurement plan should be developed in close consultation with the executing agency and resident mission staff in charge of project implementation, considering the lessons under other projects, and be flexibly adjusted. Time-consuming recruitment of many consultants along with unsuitable selection methods resulted in implementation delays. For future projects of similar nature and scope, suitable procurement packaging and selection methods should be set up based on the requirements for project progress and capacity of the EA and/or IAs.

Project Name

Strengthening Water Management and Irrigation Systems Rehabilitation Project

Project Number
42080-013
Report Date
Report Source
Self-evaluation
Country
Report Rating